Units 3, 4, 5 and 6 of the Tianwan nuclear power plant passed their final acceptance on May 31, in East China's Jiangsu province.

Units 3 and 4 - the second phase of the Tianwan plant - have a unit capacity of about 1.13 million kW. Having started construction on December 27, 2012, the two units were put into commercial operation in February and December 2018 respectively.

Units 5 and 6 - the third phase of the Tianwan plant - have a unit capacity of about 1.12 million kW. Having started construction on December 27, 2015, the two units were put into commercial operation in September 2020 and June 2021 respectively.

The China National Nuclear Power (CNNP) of the China National Nuclear Corporation (CNNC) holds a controlling stake in the Tianwan plant. Its six units have so far safely generated more than 370 billion kWh of electricity, which is equivalent to cutting carbon dioxide emissions by 303.40 million tons. This will play an important role in ensuring the energy supply of Jiangsu province, optimizing China's energy mix, promoting green and low-carbon development, as well as helping achieve the nation's carbon peaking and carbon neutrality goals.

Topics: Asia, China, NPP Tianwan


Other news:

Main Construction Phase for Unit 3 of El-Dabaa Nuclear Power Plant Commences in Egypt

A technical ceremony for the pouring of the first concrete took place.

First batch of nuclear fuel was delivered to Akkuyu NPP

The leaders of the two countries gave symbolic permission to deliver the first batch.

The CARR reactor is open to foreign customers

CARR has received more than 40 applications from abroad.


Hero of the day

Unit 2 of the Belarusian NPP included the unified energy system of the Republic of Belarus

Unit 2 of the Belarusian NPP included the unified energy system of the Republic of Belarus

The grid connection at the reactor power of 40% of the nominal one confirms the availability of all its systems and equipment for electricity generation. In the coming days, specialists will increase the reactor power up to 50% and carry out a series of dynamic tests.



INTERVIEW

AtomInfo.Ru

AtomInfo.Ru
The secondary sources are already helping to reduce the consumption of natural uranium for the operation of nuclear power plants, but the main breakthrough in the efficiency of uranium use is expected after the widespread introduction of the closed nuclear fuel cycle (NFC).


OPINION

Rosatom

Rosatom
The 12th ATOMEXPO 2022 International Forum took place in Sochi (Russia) on 21-22 November. Over 3,000 guests, including businesspeople, government agencies, and international organisations, from Russia and 65 other countries attended the event.


Search: