First unit of Belarus NPP is ready for 86-87%

AtomInfo.Ru, PUBLISHED 30.03.2019

The works for the reactor assembly on the first unit of the Belarusian nuclear power plant will be completed by the end of April.

This was reported by the ASE's vice-president Vitaly Polyanin.

"In our view, the first unit is with good dynamics. Over the past six months we have taken a significant step forward", - said Vitaly Polyanin.

According to the deputy minister of energy of Belarus Mikhail Mikhadzyuk, the readiness of the unit #1 is equal to 86-87%. The second unit is ready for 65%.

Topics: East Europe, Belarus


Other news:

Russia and China signed the Executive contracts for the construction of Tianwan NPP and Xudabao NPP

Package defines the major lines to develop cooperation between Russia and China.

WANO members vote to establish a new Branch Office and Support Centre in China

WANO has defined a high-level, three-phase deployment model for the office in Shanghai.

449 nuclear units are operating in the world

Another 55 units have the status of the being built one.


Hero of the day

Matthew Bunn: we can still work together

Matthew Bunn: we can still work together

I think the fact that the world's two largest nuclear complexes are proceeding in total isolation from each other is a danger to each of us and a danger to the rest of the world as well. And we have to find the way to fix it.



INTERVIEW

Amparo Gonzalez Espartero

Amparo Gonzalez Espartero
We are dealing with the back end of the nuclear fuel cycle until spent fuel is declared as a waste, covering storage options, reprocessing and recycling, transportation of nuclear materials and advanced fuel cycles related to Generation IV reactors.


OPINION

WANO

WANO
For each nation or region, the scope and depth of governmental supervision on export controls over organisations should be proportionate to what type of organisation it is, its track record, and the risk to proliferation it poses.


Search:


Rambler's Top100