Rosatom Mechanical Engineers Assembled Reactor Vessel for Unit 1 of El Dabaa NPP (Egypt)

Rosatom, PUBLISHED 24.03.2025

The finishing welding to connect the parts of the VVER-1200 vessel for unit 1 of the El Dabaa NPP has been finished at the Izhora Plant in St. Petersburg (the NPP is being constructed by Rosatom's Engineering division in Egypt).

The welding to connect the vessel's parts took 10 days, with the weld area being continuously heated throughout the process. Mechanical engineers used approximately 2 tons of flux and more than 1.5 tons of specialized wire to complete the job.

After the welding, the reactor vessel will undergo a heat treatment to be followed by a thorough weld quality control including X-ray flaw detection, ultrasonic and penetrant inspections. These measures are crucial to ensure safe operation of the NPP for at least six decades.

Topics: Rosatom, Egypt


Other news:

Leaders of Global Nuclear Industry to meet at World Atomic Week in Moscow

World Atomic Week international forum will take place From September 26 to September 30, 2025.

Russia and the IAEA hold another round of Interdepartmental consultations in Moscow

The parties reaffirmed their commitment to continue contacts on a regular basis.

417 nuclear units are operating in the world, 62 units are under construction

Since the beginning of 2024 six new units have been connected to the grid.


Last news:

More news

Hero of the day

Russia and Myanmar signed an intergovernmental agreement for the construction of a small modular reactor

Russia and Myanmar signed an intergovernmental agreement for the construction of a small modular reactor

The intergovernmental agreement regulates the conditions and main directions of interaction between the parties within the framework of implementation of the 110 MW SMR project with the possibility of further expansion up to 330 MW.


 

INTERVIEW

Yuriy Chernichuk

Yuriy Chernichuk
What does management mean? Financial flows, personnel policy, and investment policy can be managed. Technically, the plants will be managed by personnel who are trained in this.


OPINION

Rosatom

Rosatom
This is not just the start of a new unit construction at the Leningrad NPP-2. This is another step towards the major national goal of increasing the share of peaceful nuclear energy in the national energy mix.


Search:


Рейтинг@Mail.ru
      © AtomInfo.Ru, 2006-2025.
      Licence Эл №ФС77-30792.      ATOMINFO™ trademark.