Construction of auxiliary reactor building of Unit 1 is completed at Rooppur NPP

Communications Division of ROSATOM Engineering Division, PUBLISHED 11.04.2022

At Rooppur NPP (the People's Republic of Bangladesh, General Designer and General Contractor - ROSATOM Engineering Division), the main concrete works for the construction of auxiliary reactor building, where process instrumentation and control devices of Unit 1 are concentrated, have been completed 8 months ahead of schedule.

The facility is included in the 'nuclear island'.

The construction timeframe of the building was reduced by 241 days thanks to implementation of several RPS-projects, the main of which was 'Completion of concreting of the auxiliary reactor building cover (10UKC) at elevation +29.050'. Within the project, logistic processes were optimized and workplaces were timely provided with the required resources, first of all, with materials and tools.

The average volume of concrete laid by specialists of NIKIMT-Atomstroy JSC every month accounted for 1,600 m3 (with scheduled area output of 1,000 m3).

"The pace of work performance, achieved by the specialists of NIKIMT-Atomstroy, while keeping all the stringent requirements for the quality of works, demonstrates the highest potential of Rooppur NPP construction workers. With such degree of our employees' professionalism, it is safe to say that construction of the first NPP in Bangladesh will be completed within the scheduled dates, despite a range of personal and impersonal difficulties related to the pandemic and complex international situation", said Alexey Deriy, Vice President of ASE JSC - Project Director for Rooppur NPP Construction.

Reduction of the construction timeframe of auxiliary reactor building allowed reducing the construction cost, first of all, by means of saving a semi-fixed part of overhead costs and making available ahead of schedule a significant number of highly qualified labor resources who have already been engaged in performance of other production tasks.

Topics: Asia, Bangladesh


Other news:

Specialists of SSC RIAR have successfully completed the modernization of the VK-50 reactor

This is the first and only operating pressurized boiling reactor with natural coolant circulation in the country.

Ghana will decide on the site before the end of the year

Four candidate sites are currently being explored.

ROSATOM presents full Small Modular Reactors product line at EXPO 2020

Small Modular Reactors Day was an international platform for discussing the benefits of SMR.


Hero of the day

Fourth Hualong One unit connected to grid

Fourth Hualong One unit connected to grid

Unit 3 of the Karachi nuclear power plant in Pakistan was successfully connected to the gird on March 4, laying a solid foundation for its commercial operation.



INTERVIEW

Vladimir Kriventsev

Vladimir Kriventsev
The International Atomic Energy Agency brings together the fast reactor and related fuel cycle community and countries and the wider public interested in these technologies by organising the International Conference on Fast Reactors and Related Fuel Cycles: Sustainable Clean Energy for the Future or FR21.


OPINION

Victor Murogov

Victor Murogov
This critical analysis of the history, state, and prospects of development of modern nuclear technologies shows that nuclear energy market has practically monopolized the design and construction of only one type of reactors (95% of NPPs under construction use pressurized water reactors), which necessitates training of focused specialists involved in the construction and operation of those nuclear power plants.


Search: