Forum   Contacts   RSS
AtomInfo.Ru


The first batch of nuclear fuel has been delivered to Rooppur NPP


The official ceremony dedicated to the delivery of the first batch of nuclear fuel has been held at Rooppur NPP construction site in Bangladesh (the general designer and general contractor is Rosatom State Corporation Engineering Division)...


Installation of the outer containment dome is completed at Rooppur NPP Unit 1

At the Rooppur NPP construction site in the Peoples Republic of Bangladesh (with the Rosatom State Corporation Engineering Division being the general designer and general contractor), installation of steel structures of the outer containment dome has been completed in the reactor building of U...

The main construction and installation works are completed at Rooppur NPP (Bangladesh)

Reactor Assembly Has Been Completed at Rooppur NPP Unit 1 in Bangladesh

CIRC Wins the Bid for an Irradiation Station Project in Bangladesh

Physical startup of Ruppur-1 may occur in December - Likhachev

Passive heat removal system installed at Rooppur NPP Unit 2

Representatives of Bangladesh got acquainted with the experience of Rosenergoatom in the sphere of isotope production

Eight heat exchangers of passive heat removal system have been installed at Rooppur NPP Unit 1

Fuel supplies for the Ruppur NPP will begin in the first week of October

ROSATOM Director General Alexey Likhachev discussed the course of construction of Rooppur NPP with Prime Minister of Bangladesh Sheikh Hasina

Transport Lock Has Been Installed at Rooppur NPP Power Unit 1

Main Coolant Pipeline Welding Completed at Rooppur NPP Unit 2

Flushing of systems with the open reactor has commenced at Rooppur NPP Unit 1

Installation of the dome part of the outer containment has started at Rooppur NPP Unit 1

Bridge cranes installation completed at Unit 2 of Rooppur NPP

Concreting of the inner containment dome is completed at Rooppur NPP Unit 1

Rooppur NPP Power Unit 2 Has Started to Install the Dome Part of the Inner Containment

Works on pre-assembly of Unit 1 outer containment dome start at Rooppur NPP

Construction of auxiliary reactor building of Unit 1 is completed at Rooppur NPP

The generator stator is installed in its design position at Rooppur NPP Unit 1 (Bangladesh)

Vessel with the next batch of equipment has set off for Rooppur NPP (Bangladesh)

All news for Bangladesh

Hero of the day

Reactor pressure vessel of Xudapu NPP Unit 4 has been installed in design position

Reactor pressure vessel of Xudapu NPP Unit 4 has been installed in design position

VVER-1200 reactor is a cylindrical vessel with an elliptical bottom, inside which there is the core and the internals. The length of the equipment is 13 meters, the diameter is 4.5 meters, and the weight is 320 tons.



INTERVIEW

Rosatom

Rosatom
Pietro Barabaschi held a meeting with the management of the Institute and saw around the facilities for high-tech components manufacturing of the future plant.


OPINION

CNNC

CNNC
the 400-ton toroidal field coil TF08 of the ITER was successfully hoisted onto the sub-assembly of the Vacuum Vessel Module 1, marking another milestone in the sector module sub-assembly (SMSA).


Search: