Core catcher vessel installed at Leningrad NPP-2 unit 4 under construction

AtomInfo.Ru, PUBLISHED 30.07.2026

The core catcher vessel has been installed at the under-construction unit 4 of the Leningrad NPP-2, according to the Rosenergoatom website.

The installation of core catcher elements is carried out in stages, as the construction structures of the reactor shaft become ready.

The installation work is scheduled for completion in 2027.

Topics: Leningrad NPP, Russia, NPP


Other news:

Rosatom Enters Indian Market of Additive Manufacturing

RusBeam 2800 industrial 3D printer has successfully supplied.

Rosatom provides first nuclear fuel shipment to Xudapu NPP

Initial fuel loading for the VVER-1200 reactor at Unit 3.

Rosatom supplies the initial load of nuclear fuel for Tianwan-7

The nuclear fuel was manufactured at Novosibirsk.


Hero of the day

Presidents of Russia and Uzbekistan Mark Launch of Construction of First NPP in Uzbekistan

Presidents of Russia and Uzbekistan Mark Launch of Construction of First NPP in Uzbekistan

This milestone marks the beginning of a key stage in implementing Uzbekistan’s integrated NPP project and represents a logical continuation of the long-standing cooperation between Russia and Uzbekistan in nuclear technologies.



INTERVIEW

Rosatom

Rosatom
On November 18, in St. Petersburg, President of Russia Vladimir Putin took part via videoconference in the keel-laying ceremony for the Project 22220 sixth serial-produced universal nuclear-powered icebreaker Stalingrad.


OPINION

CNNC

CNNC
On July 12, China National Nuclear Corporation (CNNC) achieved a milestone at the "National No 1 Uranium" demonstration project in Ordos, Inner Mongolia autonomous region, producing its first barrel of uranium product.


Search: