Tianwan Nuclear Power Unit 7 completes hot functional test

CNNC, PUBLISHED 13.01.2026

On December 30, Unit 7 of CNNC's Tianwan Nuclear Power Plant successfully completed hot functional test, marking a key milestone and laying a solid foundation for subsequent nuclear fuel loading and grid connection.

Hot functional test is conducted prior to fuel loading to comprehensively verify the reliability of the nuclear and conventional island systems under hot operating conditions, ensuring all performance parameters meet design requirements.

Topics: Commissioning, Asia, China, NPP Tianwan


Other news:

Unit No. 2 has been permanently shut down at the Bilibino NPP

Units No.3 and No.4 will be shut down till end of year.

Reactor Vessel Installed at El-Dabaa NPP Power Unit 1 in Egypt

Rafael Grossi, Director General of the IAEA addressed the participants in video message.

Rosatom provides nuclear fuel for the Dalat research reactor in Vietnam

The fuel assemblies were manufactured at the Novosibirsk Chemical Concentrates Plant.


Hero of the day

Rosatom starts modernization of its third uranium enrichment plant

Rosatom starts modernization of its third uranium enrichment plant

In Seversk, Tomsk Region, the first block of high-performance 9+ generation gas centrifuges has been launched at the Isotope Separation Plant of the Siberian Chemical Combine (an enterprise of Rosatom's Nuclear Fuel Division).



INTERVIEW

Rosatom

Rosatom
On November 18, in St. Petersburg, President of Russia Vladimir Putin took part via videoconference in the keel-laying ceremony for the Project 22220 sixth serial-produced universal nuclear-powered icebreaker Stalingrad.


OPINION

CNNC

CNNC
On July 12, China National Nuclear Corporation (CNNC) achieved a milestone at the "National No 1 Uranium" demonstration project in Ordos, Inner Mongolia autonomous region, producing its first barrel of uranium product.