Forum   Contacts   RSS
AtomInfo.Ru


The Ferrosplavnaya-1 high-voltage line has been restored at the Zaporozhye Nuclear Power Plant

AtomInfo.Ru, PUBLISHED 31.12.2025

The Zaporozhye Nuclear Power Plant has completed the restoration of the line between the open switchgear of the nuclear and thermal power plants.

This line was damaged as a result of the Ukrainian Armed Forces' fire, which led to the loss of power supply to the plant from the Ferrosplavnaya-1 power line.

The repair work was carried out by the Zaporozhye Nuclear Power Plant and Rosseti specialists. The entire process was monitored by inspectors from the International Atomic Energy Agency (IAEA).

Topics: Safety, Russia, IAEA


Other news:

Unit No. 2 has been permanently shut down at the Bilibino NPP

Units No.3 and No.4 will be shut down till end of year.

Reactor Vessel Installed at El-Dabaa NPP Power Unit 1 in Egypt

Rafael Grossi, Director General of the IAEA addressed the participants in video message.

Rosatom provides nuclear fuel for the Dalat research reactor in Vietnam

The fuel assemblies were manufactured at the Novosibirsk Chemical Concentrates Plant.


Hero of the day

Rosatom starts modernization of its third uranium enrichment plant

Rosatom starts modernization of its third uranium enrichment plant

In Seversk, Tomsk Region, the first block of high-performance 9+ generation gas centrifuges has been launched at the Isotope Separation Plant of the Siberian Chemical Combine (an enterprise of Rosatom's Nuclear Fuel Division).



INTERVIEW

Rosatom

Rosatom
On November 18, in St. Petersburg, President of Russia Vladimir Putin took part via videoconference in the keel-laying ceremony for the Project 22220 sixth serial-produced universal nuclear-powered icebreaker Stalingrad.


OPINION

CNNC

CNNC
On July 12, China National Nuclear Corporation (CNNC) achieved a milestone at the "National No 1 Uranium" demonstration project in Ordos, Inner Mongolia autonomous region, producing its first barrel of uranium product.


Search: