The fifth tier of the inner containment of the reactor building installed at the Unit 3 of Akkuyu NPP construction site

Rosatom, PUBLISHED 14.08.2024

The fifth tier of the inner containment (IC) has been installed at the Akkuyu NPP Unit 3 (Turkiye). The ring-shaped welded metal structure of 396 tons and 6.5 meters high, assembled at a special site next to the power unit under construction, was moved to its regular place by a crawler crane.

The IC fifth tier is a transitional component between the cylindrical and dome parts of the containment. It consists of 12 reinforced concrete blocks (sections). The blocks began to be put together long before the installation operation. They were docked and welded together into a single ring structure of about 115 tons. Then special consoles were welded to the reinforced concrete blocks, on which a rail track was installed for the operation of a circular overhead crane (polar crane).

As a result, the weight of the structure increased to 396 tons. A hook suspension of the crane mechanism for reliable suspension of cargo on the hook weighs another 50 tons. The total weight of the cargo moved by the crawler crane was almost 450 tons.

"We completed the double assembly of the containment fifth tier at the end of 2023. The installation of the consoles to which the rail track of the polar crane is attached is usually performed already at height, after the installation of the tier. With a view of optimizing the deadlines of further construction and installation works, we decided to mount the consoles when the tier was still on the ground, and then to mount the already assembled structure in the design position. Russian and Turkish specialists - installers, crane operators, slingers - once again demonstrated the highest level of professional skill and successfully installed a multi-ton structure," stated Sergei Butckikh, Chief Executive Officer of Akkuyu Nuclear JSC.

Topics: Asia, Turkey, NPP Akkuyu


Other news:

Russian Federation and Uzbekistan sign an agreement on the construction of a small nuclear power plant

Six reactors with a capacity of 55 MW each.

Main control room of Linglong One put into operation

The Linglong One DCS has been built with China's domestically-developed Longlin and Longqi platforms.

ROSATOM showcases advanced nuclear technologies and logistical solutions at 8th Russia-China Expo

Over the past 25 years, ROSATOM and our Chinese partners have reached a high level of collaboration.


Hero of the day

Core Catcher for Unit 3 has been delivered to the Construction Site of El-Dabaa NPP

Core Catcher for Unit 3 has been delivered to the Construction Site of El-Dabaa NPP

The vessel delivering the components of the Core Catcher for Unit 3 left the port of Novorossiysk and arrived to the construction site of the El-Dabaa NPP at the end of June.



INTERVIEW

CNNC

CNNC
Ma Wenjun also emphasized that CNNC has consistently upheld an open and collaborative approach, hoping to work together with international counterparts to accelerate the development of nuclear energy, contributing to addressing challenges such as climate change and nuclear safety.


OPINION

Han Yongjiang

Han Yongjiang
To develop the new quality productive forces, it is necessary to carry out reforms to eliminate obstacles to development. In 2023, CNNC adjusted the ownership of some of its subsidiaries and formed a unified industrial platform, aiming to promote the development of the nuclear technology application industry.


Search: