On May 20th local time, the K-2 unit of the Karachi Nuclear Power Plant in Pakistan, the first overseas nuclear power unit built with China's self-developed Hualong-1 technology, met the final acceptance requirements.

Representatives from China and Pakistan jointly signed the acceptance certificate at the ceremony.

Till May 20, the construction of the first overseas nuclear power reactor equipped with China's third-generation pressurized water reactor nuclear technology, the Hualong-1, had successfully concluded.

It will inject new momentum into nuclear energy cooperation and the iron friendship between China and Pakistan, and become one of new achievements in the high-quality development of the Belt and Road Initiative (BRI).

The Pakistani side highly praised the completion of the newly-built nuclear power unit and considered the acceptance as a common honor of the two countries.

The K-2 nuclear power unit is a landmark project of the BRI and the China-Pakistan Economic Corridor, and contracted by China National Nuclear Corporation Overseas Ltd. with China's independently-developed and third-generation nuclear power technology.

It started the construction in August 2015 and came into commercial operation on May 20, 2021, setting the records for the shortest construction period and best performance of the first overseas unit Hualong-1 nuclear power technology.

At the second Belt and Road Energy Ministerial Conference, the K-2 nuclear power unit was awarded the Best Practice Case of International Energy Cooperation.

It is also the first nuclear power unit in Pakistan to achieve non-stop operation for 100 consecutive days after entering into commercial operation.

With the joint efforts of the Chinese and Pakistani sides, the K-2 nuclear power unit has shown outstanding performance since its commercial operation three years ago. All performance indicators of the nuclear power unit have further improved, with its operational standards and WANO indices achieving globally advanced level.

It has generated nearly 23 billion kilowatt-hours of electricity, which is equivalent to reducing the consumption of standard coal by 7.17 million tons annually, cutting carbon dioxide emissions by 18.76 million tons, and planting 161 million trees.

Topics: Asia, China, Pakistan


Other news:

Main control room of Linglong One put into operation

The Linglong One DCS has been built with China's domestically-developed Longlin and Longqi platforms.

ROSATOM showcases advanced nuclear technologies and logistical solutions at 8th Russia-China Expo

Over the past 25 years, ROSATOM and our Chinese partners have reached a high level of collaboration.

Theoretical ban on the sale of uranium in the United States will not cause problems for Russia

Alexey Likhachev said.

Hero of the day

Russian regulator issues the license of operation of the fuel fabrication facility for BREST-OD-300 reactor

Russian regulator issues the license of operation of the fuel fabrication facility for BREST-OD-300 reactor

The Fabrication/Refabrication Unit is facility of the Pilot Demonstration Energy Complex (PDEC), which is under construction in Seversk under the strategic "Proryv" (or "the Breakthrough" project).



INTERVIEW

CNNC

CNNC
Ma Wenjun also emphasized that CNNC has consistently upheld an open and collaborative approach, hoping to work together with international counterparts to accelerate the development of nuclear energy, contributing to addressing challenges such as climate change and nuclear safety.


OPINION

Han Yongjiang

Han Yongjiang
To develop the new quality productive forces, it is necessary to carry out reforms to eliminate obstacles to development. In 2023, CNNC adjusted the ownership of some of its subsidiaries and formed a unified industrial platform, aiming to promote the development of the nuclear technology application industry.


Search: