TEPCO unloads fresh assemblies from spent fuel pool

AtomInfo.Ru, PUBLISHED 24.11.2014

The TEPCO continues to work for unloading the fuel assemblies from the spent fuel pool of forth unit of Fukushima Daiichi NPP in Japan.

As of November 21, 2014, the 1,375 assemblies are unloaded from the pool including 1,331 irradiated and 44 fresh ones.

Totally at the time of the year 2001 accident it was 1533 assemblies in the pool. Of these, it was 1,331 irradiated and 202 fresh ones.

The unloading of irradiated assemblies has been ended in early November. Now the employees of the company unload the fresh fuel assemblies remaining in the pool.

The assemblies are discharged from the pool and placed in the general station location. The company hopes to finish unloading the pool until the end of 2014.

Topics: NPP Fukushima Daiichi


Other news:

Fuel loading completed on Rostov-3

The completion of the unit is going ahead of schedule.

Russia and Iran broaden the cooperation in the peaceful uses of atomic energy

Contract for construction of two power units of Bushehr Phase II was signed.

Spent assembly removal is completed at Fukushima Daiichi-4

180 fresh assemblies are still left in the pool.


Hero of the day

Nuclear Veterans for the Future

Nuclear Veterans for the Future

Whom should we call veterans? It is a good question. At present, we are shifting the center of gravity to persons being prepared for retirement. They still have powder in the powder-horns, they worked under market conditions, and we are going to involve them in the veteran movement.



INTERVIEW

Victor Murogov

Victor Murogov
The dual-use nature of nuclear technology consisting in the potential for its application equally in peaceful and military sphere is the basic contradiction for the existing nuclear nonproliferation regime and comprehensive development of the nuclear power and nuclear fuel cycle.


OPINION

Falling Wednesday

Falling Wednesday
Start of the third block of Olkiluoto NPP is already delayed by more than five years, and the delay will only increase.


Search:


Rambler's Top100