TEPCO plans to bring damaged nuke reactors to normal in 6-9 months

RIA Novosti, PUBLISHED April 18, 2011

Tokyo Electric Power Co., the operator of Japan's quake-hit Fukushima nuke plant, aims to bring the plant's damaged reactors to a stable condition known as a ''cold shutdown'' in about six to nine months, the Japanese news agency Kyodo reported on Sunday.

At a news conference in Tokyo, TEPCO Chairman Tsunehisa Katsumata announced the company's schedule for bringing the nuclear power plant under control, while offering an apology for the ongoing nuclear crisis, Kyodo reported.

The TEPCO management also intends to restore stable cooling to the reactors and spent fuel pools in about three months, the agency said.

TEPCO has also announced it needs three months to achieve ''steady reduction'' in radiation, and an additional three to six months to control radioactive emissions and curb radiation substantially, the agency reported.

It said it was addressing the immediate challenges of preventing hydrogen explosions at the Nos. 1 to 3 reactors and emission of water contaminated with high-level radiation from the No. 2 reactor.

It also said it will put special covers on the heavily damaged buildings of the Nos. 1, 3 and 4 reactors.

Japan's Fukushima Daiichi nuclear power plant was seriously damaged by the powerful earthquake and tsunami that hit Japan on March 11. Fukushima's operator has since been struggling to stop radioactive leaks from the plant's crippled reactors.

Topics: NPP Fukushima Daiichi


Other news:

Russia ready to finance Egypt first nuclear plant

Russia confirmed its participation in a tender to build Egypt's first nuclear power plant and said it was willing to help finance the project.

ARMZ acquires Australian uranium producer in $1.2 bln deal

ARMZ will pay eight Australian dollars per share, which represents a 15.5 percent premium on the average market price for 20 trading days.

Russia to start building Turkish NPP in 2013

Russia will start building Turkey's first NPP estimated at $20 billion in 2013, Russian ambassador to Ankara Vladimir Ivanovsky said.


Hero of the day

Alexander Chistozvonov

Alexander Chistozvonov: end of the Romantic period

Today, the army of managers is earnestly believing that one can take the man responsible for the licensing of alcoholic beverages, and put it on licensing, and even to supervise the nuclear reactor.



INTERVIEW

Christophe Behar

Christophe Behar
We are preparing now a review of these design options and the decision has to be made in 2012, by the public authorities. ASTRID basic and detailed design will be launched afterwards.


OPINION

Vladimir Rychin

Vladimir Rychin
AREVA will return the foreign workers to the uranium deposits in Niger, which have been evacuated after the September seizure of seven hostages.


Search:


Rambler's Top100