Belarus
Total electricity generation of the Belarusian NPP has reached 30 billion kWh
Rrecord of electricity consumption has been set in Belarus
Rosatom has delivered the first batch of technetium generators to Belarus
Belarusian NPP will cover more than 40 percent of Belarus electricity needs - Minister
410 nuclear units are operating in the world, 57 units are under construction
Unit 2 of the Belarusian NPP included the unified energy system of the Republic of Belarus
Unit 2 of Gen III+ with VVER-1200 (the general designer and general contractor is Rosatom Engineering Division) of the Belarusian NPP was synced with the grid for the first time and supplied the first kilowatt-hours of electricity to the unified energy system of the Republic of Belarus.
The grid connection at the reactor power of 40% of the nominal one confirms the availability of all its systems and equipment for electricity generation. In the coming days, specialists will increase the reactor power up to 50% and carry out a series of dynamic tests in order to verify the compliance of the thermal performance of the main equipment in the reactor and turbine compartments of the power unit with the design values. These tests finalize the First start stage and, after obtaining the permit from the...
Unit 2 of Belarus NPP has reached minimum controllable power level
On March 25, the reactor of Power Unit 2 of Belarus NPP (general designer and general contractor is Rosatom State Corporation Engineering Division) was brought to minimum controllable power level. At 19:42 (Moscow time), the neutron flux was registered for the first time, and controlled self-sustained nuclear reactor began.
Achievement of the minimum controllable power level (less than 1% of the rated power) makes it possible to proceed to the final part of tests of the Power Unit physical start-up stage. To confirm compliance with the design and clarify the rated neutron and physical characteristics of the reactor first fuel loading, the specialists will take measurements of the actual state of the core. Reliability of functioning of protections, interlocking and the entire...
Deputies of the RF State Duma Visiting Belarus NPP
Grid connection of unit No 2 of the Belarusian NPP is scheduled for the first quarter of 2023
First unit of the Belarusian NPP has generated 10 billion kWh of electricity since its first connection to grid
Unit 1 of the Belarusian NPP is connected to grid
The visit of experts from the WANO Moscow Center ended at the Belarusian NPP
WANO Peer Review Started at Belarusian NPP
Report of the Peer Review conducted on the Belarusian National Action Plan as part of EU Stress Test process has been published
Working meeting of Alexey Likhachev, the head of Rosatom, and Roman Golovchenko, Prime Minister of the Republic of Belarus, was held in Minsk
Nuclear News Ticker - May 02, 2021
Nuclear News Ticker - April 08, 2021
Nuclear News Ticker - March 15, 2021
Nuclear News Ticker - March 08, 2021
Nuclear News Ticker - March 05, 2021
Nuclear News Ticker - February 27, 2021
Nuclear News Ticker - February 25, 2021
Nuclear News Ticker - February 19, 2021
Nuclear News Ticker - February 11, 2021
Nuclear News Ticker - February 09, 2021
Nuclear News Ticker - January 30, 2021
Nuclear News Ticker - January 22, 2021
Power unit 1 of Belarus NPP started operation at 100% capacity
On January 12, at 19-57, the first power unit of Belarus NPP of the newest III+ generation with VVER-1200 reactor (general designer and general contractor - ROSATOM Engineering Division) was for the first time brought to rated power level.
Commencement of power ascension to 100% is the main event at the stage of trial operation of any nuclear facility power unit, said Vitaly Polyanin, ASE EC JSC project director for Belarus NPP construction.
After verification of actual parameters and characteristics of the systems and equipment operation for conformity with the design values, the power unit will be put into commercial operation.
Nuclear News Ticker - December 23, 2020
Nuclear News Ticker - December 22, 2020
Nuclear News Ticker - December 15, 2020
Nuclear News Ticker - December 11, 2020
Nuclear News Ticker - November 21, 2020
Nuclear News Ticker - November 18, 2020
Nuclear News Ticker - November 17, 2020
Nuclear News Ticker - November 13, 2020
Nuclear News Ticker - November 10, 2020
Nuclear News Ticker - November 09, 2020
Nuclear News Ticker - November 08, 2020
Nuclear News Ticker - November 07, 2020
The first power unit of the Belarus NPP has been connected to the unified power grid of the Republic of Belarus
The first kilowatt-hours of electric energy delivered by the Belarus NPP to the unified power grid system is a landmark to manifest the beginning of the nuclear age for the Republic of Belarus. This has become possible owing to the long-term and efficient work of a large team of Belarus and Russian specialists. No doubt, there is still a lot of work to be done before the unit is put into commercial operation, however it is already the case to celebrate the success of the Belarus NPP project which is the first Gen III+ nuclear power plant built by using Russian technologies outside of Russia, Alexey Likhachev, Director General of ROSATOM commented on the significant event.
The AES-2006 design, which is the basis for...
Nuclear News Ticker - November 06, 2020
443 nuclear units are operating in the world, 52 units are under construction
Nuclear News Ticker - November 04, 2020
Nuclear News Ticker - November 02, 2020
Nuclear News Ticker - November 01, 2020
Nuclear News Ticker - October 31, 2020
Nuclear News Ticker - October 30, 2020
Nuclear News Ticker - October 29, 2020
Peaceful Nuclear News - October 25, 2020
Unit No. 1 at the Belarusian Nuclear Power Plant has been brought to minimum control power
11th October 2020 2:26 a.m. Ostrovets, Belarus - Unit No. 1 at the Belarusian Nuclear Power Plant, equipped with the VVER-1200 reactor has been brought to minimum control power (MCP). Minimum control power level is reached when neutron flux is recorded in a reactor working at a level sufficient to sustain a fission chain reaction.
Reaching MCP (at a minimal power level of under 1%) is considered as the final stage of the physical start-up procedure. It allows personnel to safely take a required measurements and verify whether the physical characteristics of the reactor core comply with design requirements. In due course specialists will conduct more than 50 physical experiments on the neutronic characteristics of...
Fuel Loading Begins at Belorussian NPP Unit 1
On August 7, fuel loading began at the Belarusian NPP Unit 1. Rosatom Engineering Division is the general designer and general contractor of the NPP.
At 11:45 the first fuel assembly was loaded into the reactor of Unit 1. A total of 163 assemblies will be loaded before the end of the month.
Following the fuel loading, the reactor will reach the minimum controllable level (1% of the total power capacity) and relevant tests will be performed.
From that moment on, the reactor acquires the status of a nuclear power facility. After reliability and safety of the power unit at its design parameters are verified, the next stage of the power start-up will begin and the reactor will be connected to the grid for the first time.
The Republic of Belarus has become the owner of a power unit built according to the latest Gen 3+ technologies. This technology has been proved and tested through the operation of similar power units in Russia. They meet all the post-Fukushima safety requirements, and all the IAEA missions have...
Nuclear fuel has been delivered for initial loading to power unit 1 of Belarusian NPP
Rosatom fabricated nuclear fuel for initial loading at Unit 2 of Belarus NPP
First unit of Belarus NPP is ready for 86-87%
Nuclear fuel for the NPP will be delivered in the summer
Foreign journalists have familiarized themselves with the progress of Belarusian NPP units construction
The pre-stressing system installation has been completed at Unit 1 at Belarus NPP
Rosatom will meet the requirements of Minsk and will replace the reactor vessel for the Belarusian NPP
Russia Gives $10Bln Credit to Belarus for Nuclear Power Plant Construction
Russia Plans First Nuclear Reactor Delivery to Belarus in 2015
Belarus, Russia, Kazakhstan to Conduct Joint Counter-Terrorism Drills
Russia, Belarus to Fly Over Poland Under Open Skies Treaty
Russia, Belarus Settle Nuclear Power Plant Dispute
US, German Military Inspectors to Fly Over Russia, Belarus
A delegation of the Peoples Republic of Bangladesh paid a working visit to the construction site of Belarus NPP
German, Latvian Military Inspectors to Overfly Russia, Belarus
US, Swedish Military Inspectors to Overfly Russia, Belarus
Norwegian Military Inspectors to Fly Over Russia, Belarus
Canadian Military Inspectors to Fly over Russia, Belarus
Lithuania Urges Belarus Not to Build Nuclear Power Plant
British Military Inspectors to Fly Over Russia, Belarus
Russia Mulls Opening Branch of Skolkovo Tech Hub in Belarus
Belarus Scientists Want Logging Restart in Chernobyl Area
China to Give Belarus $16 mln Chernobyl Aid
Belarus Needs Nuclear Regulator - UN Watchdog
Russia, Belarus Sign $10 Bln Nuclear Power Plant Deal
Belarus, Russia to Sign Nuclear Plant Deal in July
Putin Visit Signals Upswing in Belarus Ties
Belarus to Receive Third Tranche of EurAsEc Bailout Loan
Russia, Belarus Initial Nuclear Power Plant Construction Deal
Belarus Ready to Build Second Nuclear Plant
Lukashenko Urges Russia to Expedite Nuke Plant Construction
Belarus agrees to Russian building of nuclear station
Belarus calls off joint nuclear fuel swap programs with USA
Russian electricity supplies to Belarus not resumed
Russia cuts off electricity supply to Belarus over debt
Russia warns Belarus on electricity debt
Ukrainian foreign ministry indignant over Lukashenko remarks
Lukashenko calls European Commission president an ass
Construction of Belarusian nuclear power plant to begin in September
Russia, Belarus to sign nuclear power plant deal in 1st quarter
Russian, Belarusian premiers to discuss energy prices, nuclear power plant
Belarus to scrap highly-enriched uranium stocks
Union State of Russia and Belarus needs intensive care
Prime Minister Vladimir Putin and his Belarusian counterpart Sergei Sidorsky will attend a meeting of the Council of Ministers of the Union State of Russia and Belarus in Moscow on October 15, 2010.
On October 5, an important event took place in Russian-Belarusian relations that went largely unnoticed. In Minsk, the transport departments of the two countries signed an agreement on transferring transport control to the external border of the Union State. Russian Transport Minister Igor Levitin said that Russia will sign a similar agreement with Kazakhstan, creating a free transport corridor in the countries of the Customs Union. And so, 19 years after the collapse of the Soviet Union, the Russian-Belarusian border is finally open.
The October 15 meeting will also be important. The sides will discuss the draft budget of the Union State for 2011. Sidorsky has indicated that both countries are actively working on this draft. He called it a growing budget, despite the post-crisis conditions.
However, official information does not always give the full picture of cooperation between Moscow and Minsk in the Union State.
Belarus to return some spent nuclear fuel to Russia
Belarus may refuse NPP construction deal with Russia - Lukashenko
Minsk to hold on to its arms-grade uranium - Lukashenko
Belarus has hundreds of kilograms of weapons-grade uranium — Lukashenko
Money row holds up Belarus's first nuclear power plant
Atomstroyexport took part in the international specialized exhibition Atomexpo Belarus
Kukshinovskaya site would be the place of first Byelorussian NPP construction
Belarus to hold tender in 2008 to build nuclear power plant
No plans to deploy nukes in Belarus
Belorussian nuclear poker
Belorussia discusses a foundation of independent regulating body for nuclear safety supervision
Russia is interested in construction of NPP in Belorussia